Frankfurt hall move
Emptying hall 2 into the new cage, and what cannot start until it is done
Open in the playground
2 Mar
9 Mar
16 Mar
23 Mar
30 Mar
6 Apr
13 Apr
20 Apr
27 Apr
2 Mar – 1 May 2026, by week
SURVEY
MOVE
WIND DOWN
Rack inventory
8d
Network design
9d
Cross-connect orders
20d
Move plan approved
Ship and rack
6d
Re-cable and power on
4d
Smoke tests
3d
Traffic in the new cage
Decommission hall 2
10d
Hand the lease back
4d
Salvage and resell
9d